What is the correct sequence of phases to follow in managing a project?

Prepare for the CAST Project Management FG IV Test. Utilize flashcards and multiple choice questions, each with hints and explanations. Achieve success in your exam!

The correct sequence of phases in managing a project is essential for ensuring that the project is executed efficiently and effectively. The chosen answer—planning, realisation, control, evaluation—accurately reflects the typical workflow of project management.

Initially, planning is crucial as it sets the foundation for the entire project. This phase involves defining the project scope, objectives, tasks, resources needed, timelines, and risk management strategies. A comprehensive planning phase ensures that all stakeholders have a clear understanding of what is to be achieved and the means to achieve it.

Following planning, the realisation phase is where the actual work takes place—tasks are executed according to the plan developed. This is when the project delivers its intended outputs and achieves its milestones. Proper execution during this phase is critical to the success of the project.

Control comes next and is an ongoing process throughout the realisation phase. It involves monitoring the project's progress against the planned objectives, ensuring that any deviations are identified and addressed promptly. Effective control mechanisms, such as performance metrics and regular status meetings, help keep the project on track and in alignment with its goals.

Finally, the evaluation phase is conducted after the project is completed. During this phase, the outcomes are assessed to determine whether the project met its objectives,