Which of the following is NOT a management mode in project management?

Prepare for the CAST Project Management FG IV Test. Utilize flashcards and multiple choice questions, each with hints and explanations. Achieve success in your exam!

Collaborative management is not typically classified as a distinct management mode in project management terminology. The primary management modes focus on how authority and responsibility are wielded within project execution.

Direct management involves a clear hierarchical structure where decisions are made by a designated leader or manager, maintaining a top-down approach. Indirect management refers to a style where influence is exerted through support and guidance rather than direct authority. Shared management emphasizes a participatory approach, allowing team members to contribute to decision-making processes collaboratively.

While collaborative management can indeed be an effective practice within teams, it is more about the philosophy of working together and not structured in the same way as the other management modes. Therefore, it does not fit as a recognized mode within the traditional framework of project management styles.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy